Saturday, May 24, 2014

24 May - acid wash done, looking good now.

24 May - Hamish and Marcus have acid wash done, looking good now.







Almost dry, and looking better...





Friday, May 23, 2014

23 May *** Final Certificate from NeoCheck ***

*** Final Certificate from NeoCheck ***

Cleaned out the shed today too.
Marcus can't make it today to acid wash tiles, maybe tomorrow.


Monday, May 19, 2014

19 May - phone calls

Soc' called from Neocheck - should have Cert tomorrow

Marcus called - will acid wash paves on Friday early


Friday, May 16, 2014

16 May. Day after bluestone pavers - needs an acid wash. Called Neocheck again

Needs an acid wash maybe ? I have let Marcus know. They finished the job in a rush and in the dark.

I have called Neocheck yet again to chase final certificate. Inspection was 28 Feb. Sigh...




Wednesday, May 14, 2014

14 May. Hamish and Marcus lay bluestone pavers and grout.

Hamish and Marcus lay bluestone pavers and grout.
Landscapit - http://www.gumtree.com.au/s-ad/craigieburn/landscaping-gardening/landscapit-constructions/1045766133

We were five short - I had to grab some more.







Long day tiling - finished at 8pm. Then we had to hose the alley... again.

Painted the last bookshelf too...


Sunday, May 4, 2014

4 May - Hamish Tiling and Carpenter Marcus quote on tiling

Hamish is tiler - looks like cousin Bruce
Marcus is carpenter - looks like cousin Tom

Total $1530 incl GST to lay 80 tiles 25 sq m.
Suggest don't seal first, do last.


Friday, May 2, 2014

2 May - Pavers from The Greenery Garden Center, Mick painting

The Greenery Garden Centre
4 Banksia St                                            
Heidelberg , VIC 3084                              
Phone:03 9459 8433
Fax:03 9459 3017
Email:courtney@thegreenery.com.au

Pavers ordered and paid for from The Greenery Garden Center 29 April from Raj. $1382 includes delivery and 10% overall discount.
Job number 139496. 80 of 800*400*20. Plus two man delivery $90
Arriving between 1300-1500, Friday 2nd.

Council is re-lining the sewer in our back lane.



Our pavers have arrived. Thanks to Mick for unloading.



Toilet roll holder on at last.


Painted stairs.