Showing posts with label Building Inspector. Show all posts
Showing posts with label Building Inspector. Show all posts

Friday, February 28, 2014

28 Feb. Final Inspection passed

Final inspection 0900-1100. Ray Heggarty. No problems other than install smoke detector upstairs - done.


Thursday, May 2, 2013

2 May. Frame Inspection passed ! Bricky finishes wall in front room. Mick and John finish roof. Alfie preps bathroom

Frame Inspection passed, 1230, Ray Heggarty from NeoCheck.

Bricky finishes wall in front room - 0900-1600
Mick and John finish roof 0700-1500.
Gutters are all finally finished. Frame built for fireplace flue.
Alfie preps bathroom 0700-1500.
Si and Alfie to Bell Plaster to order plaster, to be delivered tomorrow. Invoice 2665 $1231.38
http://www.bellplastersupplies.com.au/
















Wednesday, March 27, 2013

27 March. Wall too high. Inspector comes to look and agrees.



Onsite:
John S,  0700-1500
Building Inspector Ray Heggarty, 1200

Yup, the North wall is too high. Drop it by a certain amount.
Big discussions ensue over changing style of ceiling.

Woe. Sigh.


Tuesday, March 26, 2013

26 March. Oh no ! The North wall might be too high.


Onsite:
John S, Mick, 0700-1500 - but Johnny thinks the North wall is too high above ground level. Work stopped until Inspector comes to check.


Nothing to do but wait, eh Mick ?


Wednesday, March 13, 2013

Saturday, March 9, 2013

9 March. Finished digging kitchen footing. Inspected.

Onsite:
Mick. John S, Tony . 0700-1500 dig footings
Neocheck Surveyor   Ray Heggarty surveyor approved footing 1539
Finish digging main trenches.