2 May. Frame Inspection passed ! Bricky finishes wall in front room. Mick and John finish roof. Alfie preps bathroom

Frame Inspection passed, 1230, Ray Heggarty from NeoCheck.

Bricky finishes wall in front room - 0900-1600
Mick and John finish roof 0700-1500.
Gutters are all finally finished. Frame built for fireplace flue.
Alfie preps bathroom 0700-1500.
Si and Alfie to Bell Plaster to order plaster, to be delivered tomorrow. Invoice 2665 $1231.38