*** Final Certificate from NeoCheck ***
Cleaned out the shed today too.
Marcus can't make it today to acid wash tiles, maybe tomorrow.
Showing posts with label NeoCheck. Show all posts
Showing posts with label NeoCheck. Show all posts
Friday, May 23, 2014
Monday, May 19, 2014
19 May - phone calls
Soc' called from Neocheck - should have Cert tomorrow
Marcus called - will acid wash paves on Friday early
Marcus called - will acid wash paves on Friday early
Monday, March 31, 2014
31 Mar - called City of Yarra to chase up protection bond
called Yarra to chase up protection bond - advised inspection done and check to be posted
Called Neocheck again to chase up final certificate.
Called Neocheck again to chase up final certificate.
Friday, February 28, 2014
28 Feb. Final Inspection passed
Final inspection 0900-1100. Ray Heggarty. No problems other than install smoke detector upstairs - done.
Thursday, March 7, 2013
7 March. Tony to check site. Titan Excavations. Changing footing plans. Dig trenches.
On site Tony 1600 to check concreting
On site. Bobcat and skip. Leigh, from Titan 0700-1500
On site. Mick. John S . 0700-1500 dig footings
Si and Mick to Ratana for new footing plan. Email to Neocheck asap
On site. Bobcat and skip. Leigh, from Titan 0700-1500
On site. Mick. John S . 0700-1500 dig footings
Si and Mick to Ratana for new footing plan. Email to Neocheck asap