Monday, August 5, 2013

5 Aug. Electrical fit out. Bricks just about finished. Mick and Alf fixing stuff in general. Render ?

Mick and Alf to fit skirts and tile powder room - kitchen floor, powder room external wall.
Bricky Tony finishing off - good job too
Electrical fit out - 0730 Jordan Jimmy and Neil
Aus Lighting to deliver third flood light.
Rendering coming at 1100 ?

Pendant light above vanity looks good.


Jordan and Jimmy at work


Extra layer of bricks on North wall done


Repaired


Fixed for flashing


Mick finishing kitchen floor


Alfie putting Blueboard on external powder room wall - for rendering


Switches are in.


Tony just about finished.


Friday, August 2, 2013

2 Aug. Floorboards sanded in kitchen. Bricky Tony just about done.

Onsite - Paul and Justin sanding floorboards and collecting their gear.

Tony at 0800 to do bricks all day. It rained a little. We talked about computers and hisr remote control product. He finished the powder room wall and sill, sill for kitchen, sill for bathroom, lintel and most of pillar.







Thursday, August 1, 2013

1 Aug. . Floorboards finished - worked late. Bricks at last ! Rear gate back up.

Justin doing floorboards - 0830
Tony doing bricks 0800
Mick and John Sacco putting gate up 0730

Have messaged renderers to come Monday 5th
Emailed Bradley Snioch for quote  to weld lugs on gate pillar.


Mick, John and I have put gate and pillar back up.



Tony at work on the lintel






Justin has done a fine job on the stairs and powder room.



I help Justin to finish the front two rooms - we work until 2030 or so - stopping for Viet take away - rice and pork chop.


Done - finished. At last.




Wednesday, July 31, 2013

31 July. Floorboards - Justin ans Meesam. Potential builder Vince fell off a roof. Found a new bricky - Tony

Floorboards Justin and Meesam.
Potential builder Vince fell off a roof and broke a leg. FML.

Talked to John Sacco - he will come to build pillar reinforcing.
I am looking for brickies on Gumtree. Found three - Tony to do job.

Fence contract ends soon - contacted them - can extend month by month


More floorboards.


Jim and Julian from 1800GotJunk. Great way to get rid of stuff.


All gone. Thanks lads.



Floor all cut for the front rooms.





Monday, July 15, 2013

15 July. Sacked the bricky. What a day. Went looking for floorboards and will go Spotted Gum

Onsite John, Mick and Alf.

Started this day with paying out the bricky. Enough said.

Washed the dogs next, then went for a drive to cool down.

Went looking for floorboards and will go Spotted Gum. Had another good chat to the staff at Tait Timber. Thanks to Dianna and Peter.
Spotted Gum on special at $71.50 m2.
Hardwood timber batons at $3.45 lin m





Sunday, July 14, 2013

14 July. Bricky Mike for quote. Floor Dimensions. Paul for floor boards quote.

Sunday.

Bricky Mike Pagano dropped in for a quote on the remainder  1200
He will quote on full job, not hourly or per brick


Paul Vietnamese came to quote on floor boards 1700

Area for wood is approx 90 m2, so buy 100 m2 to allow for wastage

to lay boards $22.5 /m2 x 90 m2                                      = $2025
sand and polish with water base finish $22 /m2 x 90 m2 = $1980
- water base is expensive $1000
lay hardwood batons with proper nails $15 /m2 x 42 m2  = $630
Total = $4635 approx

Plus boards 90m2 x $70 /m2                                               = $6300
Plus batons at 34 batons x 4.5 m at $3 /m (buy 170 linear m) = $500  *** hardwood
Total with boards = $ 11435

Floors.
Old front rooms and hall = 4.8 x 8 m = 39 m2
New kitchen and toilet = 6.8 x 3.4 = 23 m2
New lounge only = 6.4 x 4.5 = 29 m2
Total = 91 m2




Friday, July 12, 2013

12 July. Sanding and plastering. Bricky called in sick - found another.

Onsite. Mick and Alf. Sanding and plastering

Brickie called in sick. Sigh. Looking for another one. Plumber Chris knows two and will forward phone numbers. Talked to bricky Stanley, he is keen and will let me know after talking to mate.




Alfie has down a fine job sorting out that box for blinds.





Mick is testing that grey paint for ceiling


Nice arse, Mick




Thursday, July 11, 2013

11 July. Bricks. Sanding and plastering.

Onsite, Mick and Alf. Plastering and sanding.

Bricky Peter and Arch. 0900-1500


Mick has hidden the conduits on both sides of front hall.



Bricked above light well door.


Alfie is trying to put plaster up on a very crooked back lintel, where the box for blinds will be.



I found a skip full of bricks. Took about 250.



Bricked, started anyway.