Friday, May 31, 2013

31 May. More tiling and plastering. All tiles done in bathroom ?

Onsite: Alf and Mick only. Finished tiles ?
More cornices from Bell Plaster













Thursday, May 30, 2013

30 May. Tiling. Plastering. Bell Plaster. Lighting.

Onsite: Alf and Mick. Tiling and fix plaster.
Plumber Nick to do more roof - but not ridge caps due to rain.

Bell Plaster deliver tomorrow.









Wednesday, May 29, 2013

29 May. Tiling bathroom. Living room ceiling batons. Finish electrical rough-in. Cornice and roof ridge arrives

Onsite: Mick, Alfie, John. Tiling, batons fro living room ceiling. 0700
All points. Neil, Jordan, Jimmy. Finish electrical rough-in. 0730
Cornice and roof ridge arrives
























Tuesday, May 28, 2013

28 May. Electrical rough-in. More tiling. Bell Plaster

Onsite: M ick, John Alf. Tiling, plastering, fixing.

Allpoints 0730 Neil Jordan Jimmy

Talked to Clas Shower Screens about cutting glass to follow shower floor slope - can do, easy.

Laura and Mick to Bell Plaster to order cornices and roses.