Wednesday, July 24, 2013

24 July. Mick and Alf - plastering and paint. Plumber Chris install gas main

Onsite Mick and Alf - plastering.

No Bricky, still sick.

Plumber Chris install gas main, gas to gas fire Heat & Glo SL350, 40 mm pipe in powder room, plumb vanity,



We need 400 Mj gas line in.


Making room for gas line...





Front room , gas line going in.



Out to the light well...




T join for kitchen and hot water...



To the gas fire in the living room



For cook top


Have lagged sewer pipe to muffle noises





Alfie has done bathroom window and door architraves..



Ohhh, shiny. Picked up bathroom light shade


Went and had dinner at the Vegie Bar, then moved all the floorboards out to clear the floor.